CLIP will enhance our existing facilities and enlarge the extent of our services. 

The existing car park will be used to build a 4-storey annex block with a 2-basement car park. 
In the annex block, there will be a prayer hall on level 2.
Level 3 and 4 will be used as prayer rooms on Sundays and a childcare centre on weekdays. 
The construction work has commenced in August 2018.

UPDATES!

NOVEMBER 2020:

SEPTEMBER 2020:

The project was 5 months away from completion before circuit breaker in April. We thank God that all workers are safe and have resume work at site since end August.  We targeted to complete the project by end Dec 2020 if the electrical sub-station could be turn on by mid Oct. The contractor from Power Grid is unable to confirm when the cable will be lay into our sub station as they have many back log projects to clear. Let pray that the electricity turn on will be on time.

NOVEMBER 2019:

CONTRIBUTE TO CLIP!

SPIRITUALLY

Pray with us for:

  • God's protection in preventing any accidents.

  • the project to complete in a timely manner.

  • the church to be able to raise the necessary funds.

  • the church to be united in vision as we embark on this journey.

FINANCIALLY

Members may give their contributions for CLIP through:

 

Bank transfer:

​OCBC

712-614957001

Cash / Cheque:

Crossed cheques made payable to "LSBC".

Please indicate "FOR CLIP" at the back of the cheque.

Open roof terrace and one prayer room

526.21 sqm

Childcare and double up as classrooms for Children’s Church

772.54 sqm

6 Carpark lots, baptismal pool, female toilets, and mechanical & electrical rooms. 
(Double up as melting pot on Sunday and events space on special events)

881.34 sqm

32 carpark lots, and 
mechanical & electrical rooms

1,384.64 sqm
CLIP Building levels outline.jpg

L5

L3

L1

B2

Roof

L4

L2

B1

128.74 SQM

Childcare and double up as classrooms for Children’s Church

649.78 sqm

MPH (around 200 pax) and use for Children’s Church on Sunday

549.93 SQM

26 carpark lots, and mechanical & electrical rooms

1,336.37 sqm
TOTAL: 6,226.54 SQM (66,997.57 SQFT)
CONSTRUCTION COST IS S$3,056/SQM or S$284/SQFT

USE OF LAND AREA

Approximate Existing Area:
3,117.6 SQM (33,545.4 SQFT)

Existing Gross Floor Area:
5,296 SQM (56,985 SQFT)

Approximate Total Area:
4,617.6 SQM (49,685.4 SQFT)

Total Gross Floor Area:
7,387 SQM (79,484 SQFT)

Approximate Additional Area:
1,500 SQM (16.140.0 SQFT)

Additional Gross Floor Area:
2,091 SQM (22,499 SQFT)

Approximate Percentage:
67% (two-thirds of land area)

Approximate Percentage:
33% (one-third of land area)

New Church Building Outline.jpg
GROSS LAND SIZE: 4,617.6SQM (49,685.4 SQFT)
PLOT RATIO OF 1.6

SUMMARY OF PROJECT COST

Government, Consultation, and Inspection Fees

Building

Fire Protection

Air Conditioning

Electrical

Lifts

Provisional & Contingency Sum

TOTAL

S$ 1,581,164.14
S$ 14,364,750.00
S$ 288,900.00
S$ 475,812.95
S$ 798,220.00
S$ 264,290.00
S$ 1,253,000.00
S$ 19,026,137.09

EXPECTED PAYMENTS

(Paid) Jan 2019

Mar 2019

May 2019

Jul 2019

Sep 2019

Nov 2019

Jan 2020

Mar 2020

May 2020

Jul 2020

(Retention Sum) Jul 2021

S$ 3,338,462.17
S$ 5,350,000.00
S$ 6,800,000.00
S$ 8,300,000.00
S$ 9,923,000.00
S$ 12,019,000.00
S$ 14,054,000.00
S$ 16,070,000.00
S$ 17,100,000.00
S$ 18,550,483.67
S$ 19,026,137.09

SUMMARY OF CONSTRUCTION PROGRAMME

Site mobilisation and set up

AUG 2018 - SEP 2018

Piling work

OCT 2018 - FEB 2019

Basement work

FEB 2019 - JUL 2019

1st to 4th Story (Superstructure)

APR 2019 - OCT 2019

1st to 4th Story (Architectural)

JUL 2019 - MAR 2020

External work

NOV 2019 - MAY 2020

Inspections

APR 2020 - MAY 2020

Completion

JUN 2020